DETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM

Purpose. In paper the most efficient and economical way for bringing the grounding system of power facilities into compliance with requirements of normative parameters was determined. Methodology. The determination was based on the comparison of the calculated values of touch voltage and length of a...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: S.S. Rudenko, D.G. Koliushko, O.V. Kashcheyev
Formato: article
Lenguaje:EN
RU
UK
Publicado: National Technical University "Kharkiv Polytechnic Institute" 2017
Materias:
Acceso en línea:https://doaj.org/article/3082dfb575ab438fb1926e84fa1873ae
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
id oai:doaj.org-article:3082dfb575ab438fb1926e84fa1873ae
record_format dspace
spelling oai:doaj.org-article:3082dfb575ab438fb1926e84fa1873ae2021-12-02T16:19:12ZDETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM10.20998/2074-272X.2017.2.092074-272X2309-3404https://doaj.org/article/3082dfb575ab438fb1926e84fa1873ae2017-04-01T00:00:00Zhttp://eie.khpi.edu.ua/article/view/2074-272X.2017.2.09/95898https://doaj.org/toc/2074-272Xhttps://doaj.org/toc/2309-3404Purpose. In paper the most efficient and economical way for bringing the grounding system of power facilities into compliance with requirements of normative parameters was determined. Methodology. The determination was based on the comparison of the calculated values of touch voltage and length of additional electrodes for reconstruction of grounding system by two ways. To calculate the software based on the method of point current source which located in the three-layer soil, method guidance potential, Gauss method and the method of ordinary least squares was used. Results. For three possible cases amount of material and labor costs for the reconstruction and modernization of the grounding system while maintaining the equipotent grounding system and allowable touch voltage was defined. Originality. For the first time the effectiveness the reconstruction of grounding system for requirements of touch voltage, not to her of resistance, both in terms of electrical safety and in terms of material and labor costs proved. Practical value. The implementation of results saves a national scale funds for modernization and reconstruction of existing grounding systems of power facilities.S.S. RudenkoD.G. KoliushkoO.V. KashcheyevNational Technical University "Kharkiv Polytechnic Institute"articlegrounding systemelectrical safetyreconstructionmaterial and labour costsElectrical engineering. Electronics. Nuclear engineeringTK1-9971ENRUUKElectrical engineering & Electromechanics, Iss 2, Pp 57-61 (2017)
institution DOAJ
collection DOAJ
language EN
RU
UK
topic grounding system
electrical safety
reconstruction
material and labour costs
Electrical engineering. Electronics. Nuclear engineering
TK1-9971
spellingShingle grounding system
electrical safety
reconstruction
material and labour costs
Electrical engineering. Electronics. Nuclear engineering
TK1-9971
S.S. Rudenko
D.G. Koliushko
O.V. Kashcheyev
DETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM
description Purpose. In paper the most efficient and economical way for bringing the grounding system of power facilities into compliance with requirements of normative parameters was determined. Methodology. The determination was based on the comparison of the calculated values of touch voltage and length of additional electrodes for reconstruction of grounding system by two ways. To calculate the software based on the method of point current source which located in the three-layer soil, method guidance potential, Gauss method and the method of ordinary least squares was used. Results. For three possible cases amount of material and labor costs for the reconstruction and modernization of the grounding system while maintaining the equipotent grounding system and allowable touch voltage was defined. Originality. For the first time the effectiveness the reconstruction of grounding system for requirements of touch voltage, not to her of resistance, both in terms of electrical safety and in terms of material and labor costs proved. Practical value. The implementation of results saves a national scale funds for modernization and reconstruction of existing grounding systems of power facilities.
format article
author S.S. Rudenko
D.G. Koliushko
O.V. Kashcheyev
author_facet S.S. Rudenko
D.G. Koliushko
O.V. Kashcheyev
author_sort S.S. Rudenko
title DETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM
title_short DETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM
title_full DETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM
title_fullStr DETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM
title_full_unstemmed DETERMINATION OF DIRECTION TO RECONSTRUCTION OF GROUNDING SYSTEM
title_sort determination of direction to reconstruction of grounding system
publisher National Technical University "Kharkiv Polytechnic Institute"
publishDate 2017
url https://doaj.org/article/3082dfb575ab438fb1926e84fa1873ae
work_keys_str_mv AT ssrudenko determinationofdirectiontoreconstructionofgroundingsystem
AT dgkoliushko determinationofdirectiontoreconstructionofgroundingsystem
AT ovkashcheyev determinationofdirectiontoreconstructionofgroundingsystem
_version_ 1718384161652211712