Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia

Today, several developing countries struggle to improve the cost and time performances of major infrastructure works due to various reasons. Cost overrun and delay are one of the major challenges being faced by the construction and infrastructure sector. Hence, the aim of this study is to explore th...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: Solomon Melaku Belay, Seifu Tilahun, Mitiku Yehualaw, Jose Matos, Helder Sousa, Endalew Temesgen Workneh
Formato: article
Lenguaje:EN
Publicado: Hindawi Limited 2021
Materias:
Acceso en línea:https://doaj.org/article/68700f77278746b380bad62df9086f23
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
id oai:doaj.org-article:68700f77278746b380bad62df9086f23
record_format dspace
spelling oai:doaj.org-article:68700f77278746b380bad62df9086f232021-11-29T00:55:55ZAnalysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia1687-809410.1155/2021/4991204https://doaj.org/article/68700f77278746b380bad62df9086f232021-01-01T00:00:00Zhttp://dx.doi.org/10.1155/2021/4991204https://doaj.org/toc/1687-8094Today, several developing countries struggle to improve the cost and time performances of major infrastructure works due to various reasons. Cost overrun and delay are one of the major challenges being faced by the construction and infrastructure sector. Hence, the aim of this study is to explore the extent of cost overrun and schedule delays in building and road infrastructure projects across the Ethiopian construction industry. Primary data were collected through a structured questionnaire survey to evaluate the potential risks leading to those challenges. Various data analysis tools were employed, to investigate the critical causes of cost overrun and delays in infrastructure projects. The findings reveal that the minimum cost overrun for building construction projects is found to be 2%, whereas the maximum and average cost overruns are 248% and 35%, respectively. For road infrastructure projects, the minimum, maximum, and average cost overruns are found to be 1%, 61%, and 18%, respectively. Similarly, the minimum, maximum, and average delays recorded in building construction projects are 9%, 802%, and 143%, respectively, whereas, in road infrastructure projects, the minimum delay is found to be 3%, the maximum delay is 312%, and an average schedule delay of 110% is recorded. In addition, the top risk factors leading to cost overrun in infrastructure projects are inflation, inaccurate cost estimates, and variations, whereas the major risks causing schedule delays are variations, economic conditions, and escalation of material prices. Further, practical implications and key recommendations were provided to curb cost overrun and delay in infrastructure projects.Solomon Melaku BelaySeifu TilahunMitiku YehualawJose MatosHelder SousaEndalew Temesgen WorknehHindawi LimitedarticleEngineering (General). Civil engineering (General)TA1-2040ENAdvances in Civil Engineering, Vol 2021 (2021)
institution DOAJ
collection DOAJ
language EN
topic Engineering (General). Civil engineering (General)
TA1-2040
spellingShingle Engineering (General). Civil engineering (General)
TA1-2040
Solomon Melaku Belay
Seifu Tilahun
Mitiku Yehualaw
Jose Matos
Helder Sousa
Endalew Temesgen Workneh
Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
description Today, several developing countries struggle to improve the cost and time performances of major infrastructure works due to various reasons. Cost overrun and delay are one of the major challenges being faced by the construction and infrastructure sector. Hence, the aim of this study is to explore the extent of cost overrun and schedule delays in building and road infrastructure projects across the Ethiopian construction industry. Primary data were collected through a structured questionnaire survey to evaluate the potential risks leading to those challenges. Various data analysis tools were employed, to investigate the critical causes of cost overrun and delays in infrastructure projects. The findings reveal that the minimum cost overrun for building construction projects is found to be 2%, whereas the maximum and average cost overruns are 248% and 35%, respectively. For road infrastructure projects, the minimum, maximum, and average cost overruns are found to be 1%, 61%, and 18%, respectively. Similarly, the minimum, maximum, and average delays recorded in building construction projects are 9%, 802%, and 143%, respectively, whereas, in road infrastructure projects, the minimum delay is found to be 3%, the maximum delay is 312%, and an average schedule delay of 110% is recorded. In addition, the top risk factors leading to cost overrun in infrastructure projects are inflation, inaccurate cost estimates, and variations, whereas the major risks causing schedule delays are variations, economic conditions, and escalation of material prices. Further, practical implications and key recommendations were provided to curb cost overrun and delay in infrastructure projects.
format article
author Solomon Melaku Belay
Seifu Tilahun
Mitiku Yehualaw
Jose Matos
Helder Sousa
Endalew Temesgen Workneh
author_facet Solomon Melaku Belay
Seifu Tilahun
Mitiku Yehualaw
Jose Matos
Helder Sousa
Endalew Temesgen Workneh
author_sort Solomon Melaku Belay
title Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
title_short Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
title_full Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
title_fullStr Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
title_full_unstemmed Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
title_sort analysis of cost overrun and schedule delays of infrastructure projects in low income economies: case studies in ethiopia
publisher Hindawi Limited
publishDate 2021
url https://doaj.org/article/68700f77278746b380bad62df9086f23
work_keys_str_mv AT solomonmelakubelay analysisofcostoverrunandscheduledelaysofinfrastructureprojectsinlowincomeeconomiescasestudiesinethiopia
AT seifutilahun analysisofcostoverrunandscheduledelaysofinfrastructureprojectsinlowincomeeconomiescasestudiesinethiopia
AT mitikuyehualaw analysisofcostoverrunandscheduledelaysofinfrastructureprojectsinlowincomeeconomiescasestudiesinethiopia
AT josematos analysisofcostoverrunandscheduledelaysofinfrastructureprojectsinlowincomeeconomiescasestudiesinethiopia
AT heldersousa analysisofcostoverrunandscheduledelaysofinfrastructureprojectsinlowincomeeconomiescasestudiesinethiopia
AT endalewtemesgenworkneh analysisofcostoverrunandscheduledelaysofinfrastructureprojectsinlowincomeeconomiescasestudiesinethiopia
_version_ 1718407712025346048