ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK

Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week sh...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: G.A.P Candra Dharmayanti, I Gusti Agung Adnyana Putera, Made Yoga Prasetya
Formato: article
Lenguaje:ID
Publicado: Universitas Udayana 2021
Materias:
Acceso en línea:https://doaj.org/article/8350a4ea95d1410995ddb68fe12b49bb
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
id oai:doaj.org-article:8350a4ea95d1410995ddb68fe12b49bb
record_format dspace
spelling oai:doaj.org-article:8350a4ea95d1410995ddb68fe12b49bb2021-11-28T13:31:57ZANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK1411-12922541-548410.24843/JITS.2021.v25.i01.p10https://doaj.org/article/8350a4ea95d1410995ddb68fe12b49bb2021-01-01T00:00:00Zhttps://ojs.unud.ac.id/index.php/jits/article/view/70910https://doaj.org/toc/1411-1292https://doaj.org/toc/2541-5484Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week showed a 3,76% delay in project implementation. This affects the project completion time and the contractor may be subject to penalty for the delay. This study’s purpose to design a schedule to get the acceleration of construction time using the fast track method and compare the results obtained by the conditions of project implementation experiencing delays. Secondary data used include time schedules, budget plans (RAB), weekly reports of supervisory consultants, analysis of contractor unit prices, and project drawings. The value of the implementation budget plan (RAP) is Rp45.917.529.226,76 calculated based on the RAB of the contractor without taxes and profits. The results of the analysis using the fast track method show that the project can be accelerated so that it can be finished according to the planned schedule by accelerating by 59 days (22,7%) from the duration of project implementation in a late condition (without acceleration). In terms of cost, project implementation in a late condition incurs more costs than the project implementation using the fast track method. The magnitude of the additional costs of implementing the project with a late condition of Rp2.656.202.803,55 or 5,468% more than the application of the fast track method. The application of the fast track method results in changes in the number of workers and material procurement needs at a time caused by the time shifts in activities implemented out in parallel.G.A.P Candra DharmayantiI Gusti Agung Adnyana PuteraMade Yoga PrasetyaUniversitas UdayanaarticleEngineering (General). Civil engineering (General)TA1-2040IDJurnal Ilmiah Teknik Sipil, Vol 25, Iss 1, Pp 83-92 (2021)
institution DOAJ
collection DOAJ
language ID
topic Engineering (General). Civil engineering (General)
TA1-2040
spellingShingle Engineering (General). Civil engineering (General)
TA1-2040
G.A.P Candra Dharmayanti
I Gusti Agung Adnyana Putera
Made Yoga Prasetya
ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK
description Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week showed a 3,76% delay in project implementation. This affects the project completion time and the contractor may be subject to penalty for the delay. This study’s purpose to design a schedule to get the acceleration of construction time using the fast track method and compare the results obtained by the conditions of project implementation experiencing delays. Secondary data used include time schedules, budget plans (RAB), weekly reports of supervisory consultants, analysis of contractor unit prices, and project drawings. The value of the implementation budget plan (RAP) is Rp45.917.529.226,76 calculated based on the RAB of the contractor without taxes and profits. The results of the analysis using the fast track method show that the project can be accelerated so that it can be finished according to the planned schedule by accelerating by 59 days (22,7%) from the duration of project implementation in a late condition (without acceleration). In terms of cost, project implementation in a late condition incurs more costs than the project implementation using the fast track method. The magnitude of the additional costs of implementing the project with a late condition of Rp2.656.202.803,55 or 5,468% more than the application of the fast track method. The application of the fast track method results in changes in the number of workers and material procurement needs at a time caused by the time shifts in activities implemented out in parallel.
format article
author G.A.P Candra Dharmayanti
I Gusti Agung Adnyana Putera
Made Yoga Prasetya
author_facet G.A.P Candra Dharmayanti
I Gusti Agung Adnyana Putera
Made Yoga Prasetya
author_sort G.A.P Candra Dharmayanti
title ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK
title_short ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK
title_full ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK
title_fullStr ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK
title_full_unstemmed ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK
title_sort analisis percepatan pelaksanaan proyek unit layanan kanker terpadu rsud bali mandara dengan metode fast track
publisher Universitas Udayana
publishDate 2021
url https://doaj.org/article/8350a4ea95d1410995ddb68fe12b49bb
work_keys_str_mv AT gapcandradharmayanti analisispercepatanpelaksanaanproyekunitlayanankankerterpadursudbalimandaradenganmetodefasttrack
AT igustiagungadnyanaputera analisispercepatanpelaksanaanproyekunitlayanankankerterpadursudbalimandaradenganmetodefasttrack
AT madeyogaprasetya analisispercepatanpelaksanaanproyekunitlayanankankerterpadursudbalimandaradenganmetodefasttrack
_version_ 1718407841805500416