ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK

Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week sh...