Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning

Abstract The impoundment of the Three Gorges Dam on the Yangtze River begins in 2003 and a full pool level is first attained in 2010. This process leads to reciprocal adjustments in flow discharge, sediment transport and morphology downstream of the dam. Based on 26-year recorded hydrologic data 199...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: Qiancheng Xie, James Yang, T. Staffan Lundström
Formato: article
Lenguaje:EN
Publicado: Nature Portfolio 2021
Materias:
R
Q
Acceso en línea:https://doaj.org/article/d3f4f793cb24457796e88228852ae145
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
id oai:doaj.org-article:d3f4f793cb24457796e88228852ae145
record_format dspace
spelling oai:doaj.org-article:d3f4f793cb24457796e88228852ae1452021-12-02T16:32:08ZSediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning10.1038/s41598-021-93004-22045-2322https://doaj.org/article/d3f4f793cb24457796e88228852ae1452021-07-01T00:00:00Zhttps://doi.org/10.1038/s41598-021-93004-2https://doaj.org/toc/2045-2322Abstract The impoundment of the Three Gorges Dam on the Yangtze River begins in 2003 and a full pool level is first attained in 2010. This process leads to reciprocal adjustments in flow discharge, sediment transport and morphology downstream of the dam. Based on 26-year recorded hydrologic data 1990–2015 and surveyed bathymetries 1998, 2010 and 2015, this study elucidates, before and after the commissioning of the dam, the alterations along the 500-km reach of the river. Two-dimensional numerical simulations are performed to predict future morphological changes by 2025. The analyses demonstrate that the impoundment modulates the seasonal flow discharges and traps an appreciable amount of sediment, resulting in enhanced erosion potential and coarsening of sediment. On a multi-year basis, the maximum discharge varies by a factor of 1.3 and the corresponding suspended load concentration and transport rate differ by a factor of 3.0 and 3.8, respectively. Combinations of surveyed and simulated bathymetries reveal its morphological responses to the changes. A general pattern of erosion is observed along the reach. In its upper 120 km, the process slows down towards 2025. In the middle 200 km, the erosion shifts, following the gradual impounding, to slight deposition, which then shifts back to erosion around September 2018. In the final 180 km, erosion continues without any sign of de-escalation, which is presumedly ascribed to tidal actions. The reach has not yet achieved a hydro-morphological equilibrium; the riverbed down-cutting is supposed to continue for a while. The combination of the field and numerical investigations provides, with the elapse of time, insight into the morpho-dynamics in the 500 km river reach.Qiancheng XieJames YangT. Staffan LundströmNature PortfolioarticleMedicineRScienceQENScientific Reports, Vol 11, Iss 1, Pp 1-17 (2021)
institution DOAJ
collection DOAJ
language EN
topic Medicine
R
Science
Q
spellingShingle Medicine
R
Science
Q
Qiancheng Xie
James Yang
T. Staffan Lundström
Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning
description Abstract The impoundment of the Three Gorges Dam on the Yangtze River begins in 2003 and a full pool level is first attained in 2010. This process leads to reciprocal adjustments in flow discharge, sediment transport and morphology downstream of the dam. Based on 26-year recorded hydrologic data 1990–2015 and surveyed bathymetries 1998, 2010 and 2015, this study elucidates, before and after the commissioning of the dam, the alterations along the 500-km reach of the river. Two-dimensional numerical simulations are performed to predict future morphological changes by 2025. The analyses demonstrate that the impoundment modulates the seasonal flow discharges and traps an appreciable amount of sediment, resulting in enhanced erosion potential and coarsening of sediment. On a multi-year basis, the maximum discharge varies by a factor of 1.3 and the corresponding suspended load concentration and transport rate differ by a factor of 3.0 and 3.8, respectively. Combinations of surveyed and simulated bathymetries reveal its morphological responses to the changes. A general pattern of erosion is observed along the reach. In its upper 120 km, the process slows down towards 2025. In the middle 200 km, the erosion shifts, following the gradual impounding, to slight deposition, which then shifts back to erosion around September 2018. In the final 180 km, erosion continues without any sign of de-escalation, which is presumedly ascribed to tidal actions. The reach has not yet achieved a hydro-morphological equilibrium; the riverbed down-cutting is supposed to continue for a while. The combination of the field and numerical investigations provides, with the elapse of time, insight into the morpho-dynamics in the 500 km river reach.
format article
author Qiancheng Xie
James Yang
T. Staffan Lundström
author_facet Qiancheng Xie
James Yang
T. Staffan Lundström
author_sort Qiancheng Xie
title Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning
title_short Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning
title_full Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning
title_fullStr Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning
title_full_unstemmed Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning
title_sort sediment and morphological changes along yangtze river’s 500 km between datong and xuliujing before and after three gorges dam commissioning
publisher Nature Portfolio
publishDate 2021
url https://doaj.org/article/d3f4f793cb24457796e88228852ae145
work_keys_str_mv AT qianchengxie sedimentandmorphologicalchangesalongyangtzerivers500kmbetweendatongandxuliujingbeforeandafterthreegorgesdamcommissioning
AT jamesyang sedimentandmorphologicalchangesalongyangtzerivers500kmbetweendatongandxuliujingbeforeandafterthreegorgesdamcommissioning
AT tstaffanlundstrom sedimentandmorphologicalchangesalongyangtzerivers500kmbetweendatongandxuliujingbeforeandafterthreegorgesdamcommissioning
_version_ 1718383837864525824