Optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function

Considering that the mission of the project organization management is to create a commitment to the timetable, which prevents project delays and increases associated costs, and accept the fact that the delay in the completion time of the project results in the non-economization of the project, Ther...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: Mohammad Javad Taheri Amiri, farshidreza haghighi, Ehsan Eshtehardian, Milad Hemmatian, Roham khaleghnejad
Formato: article
Lenguaje:FA
Publicado: Iranian Society of Structrual Engineering (ISSE) 2020
Materias:
Acceso en línea:https://doaj.org/article/e1210aeddfc7434e87a5294dfe134d40
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
id oai:doaj.org-article:e1210aeddfc7434e87a5294dfe134d40
record_format dspace
spelling oai:doaj.org-article:e1210aeddfc7434e87a5294dfe134d402021-11-08T15:54:03ZOptimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function2476-39772538-261610.22065/jsce.2019.122218.1496https://doaj.org/article/e1210aeddfc7434e87a5294dfe134d402020-10-01T00:00:00Zhttps://www.jsce.ir/article_81545_d41d8cd98f00b204e9800998ecf8427e.pdfhttps://doaj.org/toc/2476-3977https://doaj.org/toc/2538-2616Considering that the mission of the project organization management is to create a commitment to the timetable, which prevents project delays and increases associated costs, and accept the fact that the delay in the completion time of the project results in the non-economization of the project, Therefore, the necessity of using proper planning and control methods seems necessary. One of the new methods used in project planning and control, which today focuses on many researchers, is the critical chain management method. In this research, multi-project scheduling with resource constraint in the critical-chain model has been investigated. In general, RCMPSP seeks to find the right sequence for project activities, so that the constraints of the priority of the project network and the various types of resource constraints in the project are met simultaneously. To this end, a multi-objective optimization model has been developed to solve this problem, with its stated objectives, the completion time of the entire project, the cost of the overall project implementation, and the quality of the implementation of the project activities. Also, the critical chain approach, as a new method of project management, has been used for project scheduling and particle swarm optimization algorithm for solving proposed model of this research.Mohammad Javad Taheri Amirifarshidreza haghighiEhsan EshtehardianMilad HemmatianRoham khaleghnejadIranian Society of Structrual Engineering (ISSE)articlemulti projectresource constraintproject schedulingcritical chainparticle swarm optimization algorithmBridge engineeringTG1-470Building constructionTH1-9745FAJournal of Structural and Construction Engineering, Vol 7, Iss شماره ویژه 3, Pp 87-108 (2020)
institution DOAJ
collection DOAJ
language FA
topic multi project
resource constraint
project scheduling
critical chain
particle swarm optimization algorithm
Bridge engineering
TG1-470
Building construction
TH1-9745
spellingShingle multi project
resource constraint
project scheduling
critical chain
particle swarm optimization algorithm
Bridge engineering
TG1-470
Building construction
TH1-9745
Mohammad Javad Taheri Amiri
farshidreza haghighi
Ehsan Eshtehardian
Milad Hemmatian
Roham khaleghnejad
Optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function
description Considering that the mission of the project organization management is to create a commitment to the timetable, which prevents project delays and increases associated costs, and accept the fact that the delay in the completion time of the project results in the non-economization of the project, Therefore, the necessity of using proper planning and control methods seems necessary. One of the new methods used in project planning and control, which today focuses on many researchers, is the critical chain management method. In this research, multi-project scheduling with resource constraint in the critical-chain model has been investigated. In general, RCMPSP seeks to find the right sequence for project activities, so that the constraints of the priority of the project network and the various types of resource constraints in the project are met simultaneously. To this end, a multi-objective optimization model has been developed to solve this problem, with its stated objectives, the completion time of the entire project, the cost of the overall project implementation, and the quality of the implementation of the project activities. Also, the critical chain approach, as a new method of project management, has been used for project scheduling and particle swarm optimization algorithm for solving proposed model of this research.
format article
author Mohammad Javad Taheri Amiri
farshidreza haghighi
Ehsan Eshtehardian
Milad Hemmatian
Roham khaleghnejad
author_facet Mohammad Javad Taheri Amiri
farshidreza haghighi
Ehsan Eshtehardian
Milad Hemmatian
Roham khaleghnejad
author_sort Mohammad Javad Taheri Amiri
title Optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function
title_short Optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function
title_full Optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function
title_fullStr Optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function
title_full_unstemmed Optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function
title_sort optimization of time, cost and quality in critical chain method in multi project scheduling and resource constraints with considering utility function
publisher Iranian Society of Structrual Engineering (ISSE)
publishDate 2020
url https://doaj.org/article/e1210aeddfc7434e87a5294dfe134d40
work_keys_str_mv AT mohammadjavadtaheriamiri optimizationoftimecostandqualityincriticalchainmethodinmultiprojectschedulingandresourceconstraintswithconsideringutilityfunction
AT farshidrezahaghighi optimizationoftimecostandqualityincriticalchainmethodinmultiprojectschedulingandresourceconstraintswithconsideringutilityfunction
AT ehsaneshtehardian optimizationoftimecostandqualityincriticalchainmethodinmultiprojectschedulingandresourceconstraintswithconsideringutilityfunction
AT miladhemmatian optimizationoftimecostandqualityincriticalchainmethodinmultiprojectschedulingandresourceconstraintswithconsideringutilityfunction
AT rohamkhaleghnejad optimizationoftimecostandqualityincriticalchainmethodinmultiprojectschedulingandresourceconstraintswithconsideringutilityfunction
_version_ 1718441617595039744