Qualitative Analysis of Risks Affecting the Delivery of Land Surveying Project Activities
Land surveying projects (LSPs) suffer from the effects of many risk factors on the time and accuracy of these projects. Using field surveys, the main objective of this study was identifying the major activities and risk factors associated with LSPs’ execution, as well as assessing and analyzing the...
Guardado en:
Autores principales: | , , |
---|---|
Formato: | article |
Lenguaje: | EN |
Publicado: |
MDPI AG
2021
|
Materias: | |
Acceso en línea: | https://doaj.org/article/f3d6bf6fa8b746b9b0cb353b7f0b1462 |
Etiquetas: |
Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
|
Sumario: | Land surveying projects (LSPs) suffer from the effects of many risk factors on the time and accuracy of these projects. Using field surveys, the main objective of this study was identifying the major activities and risk factors associated with LSPs’ execution, as well as assessing and analyzing the effects of the risk factors on the LSPs’ time and accuracy. Furthermore, the study aimed to classify and determine the responsibility of each risk factor and evaluate the responsibilities. Four main activities were categorized and presented, including reconnaissance works, planning works, data collection works, and data adjustment works. Moreover, forty-three risk factors that control the main activities and affect the time and accuracy of LSPs were recognized. The probabilities of occurrences for the risk factors and impacts on the time and accuracy of LSPs were determined as well as their combined effects. Key risk factors that had high threats on LSPs and affect time and accuracy were highlighted as the most critical risk factors. Many correlations were determined among risk factors affecting LSPs’ activity groups and their various effects on time and accuracy. The responsibilities of the surveying crew (chief, surveyor, assistance, office engineer) for each risk factors were correspondingly defined. The results showed that “Data collection works” is considered the riskiest activity group in LSPs and most of the key risk factors belonged to this group. Around 25% of the LSPs face time overrun and do not meet the required specifications. On the other hand, the surveyor was found to be responsible for most of the risk factors and the office engineer was signified by the lowest responsibility, while the responsibilities for most risk factors were single responsibility and few were shared by only dual responsibility. |
---|