Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study

In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: Arriagada,Ricardo E, Alarcón C,Luis F
Lenguaje:English
Publicado: Escuela de Construcción Civil, Pontificia Universidad Católica de Chile 2014
Materias:
Acceso en línea:http://www.scielo.cl/scielo.php?script=sci_arttext&pid=S0718-915X2014000100001
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
id oai:scielo:S0718-915X2014000100001
record_format dspace
spelling oai:scielo:S0718-915X20140001000012014-11-06Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case StudyArriagada,Ricardo EAlarcón C,Luis F Probabilistic model working day extended productivity loss mining project case study In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to submit to arbitration by an external agency, to determine and quantify the existence of lost productivity caused by the change of work schedules. The external agency considered three basic elements: a) the temporal dimension to allow the comparison of two work schedules, b) the acceptable range of productivity losses associated with these schedules; and c) an unbiased mechanism to allocate a productivity loss within the range associated with each schedule. This paper presents the analysis of productivity loss when work schedules are extended, the method utilized, and the results obtained. This probabilistic model randomly assigns discrete values of productivity loss for each day of the work schedules, and uses inefficiency ranges from industry research; this allows a non-biased, easy to implement, comparison of work schedules.info:eu-repo/semantics/openAccessEscuela de Construcción Civil, Pontificia Universidad Católica de ChileRevista de la construcción v.13 n.1 20142014-04-01text/htmlhttp://www.scielo.cl/scielo.php?script=sci_arttext&pid=S0718-915X2014000100001en10.4067/S0718-915X2014000100001
institution Scielo Chile
collection Scielo Chile
language English
topic Probabilistic model
working day extended
productivity loss
mining project
case study
spellingShingle Probabilistic model
working day extended
productivity loss
mining project
case study
Arriagada,Ricardo E
Alarcón C,Luis F
Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
description In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to submit to arbitration by an external agency, to determine and quantify the existence of lost productivity caused by the change of work schedules. The external agency considered three basic elements: a) the temporal dimension to allow the comparison of two work schedules, b) the acceptable range of productivity losses associated with these schedules; and c) an unbiased mechanism to allocate a productivity loss within the range associated with each schedule. This paper presents the analysis of productivity loss when work schedules are extended, the method utilized, and the results obtained. This probabilistic model randomly assigns discrete values of productivity loss for each day of the work schedules, and uses inefficiency ranges from industry research; this allows a non-biased, easy to implement, comparison of work schedules.
author Arriagada,Ricardo E
Alarcón C,Luis F
author_facet Arriagada,Ricardo E
Alarcón C,Luis F
author_sort Arriagada,Ricardo E
title Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
title_short Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
title_full Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
title_fullStr Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
title_full_unstemmed Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
title_sort quantification of productivity changes due to work schedule changes in construction projects: a case study
publisher Escuela de Construcción Civil, Pontificia Universidad Católica de Chile
publishDate 2014
url http://www.scielo.cl/scielo.php?script=sci_arttext&pid=S0718-915X2014000100001
work_keys_str_mv AT arriagadaricardoe quantificationofproductivitychangesduetoworkschedulechangesinconstructionprojectsacasestudy
AT alarconcluisf quantificationofproductivitychangesduetoworkschedulechangesinconstructionprojectsacasestudy
_version_ 1714206265945620480