Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to...
Guardado en:
Autores principales: | Arriagada,Ricardo E, Alarcón C,Luis F |
---|---|
Lenguaje: | English |
Publicado: |
Escuela de Construcción Civil, Pontificia Universidad Católica de Chile
2014
|
Materias: | |
Acceso en línea: | http://www.scielo.cl/scielo.php?script=sci_arttext&pid=S0718-915X2014000100001 |
Etiquetas: |
Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
|
Ejemplares similares
-
Recommendations for outpatient activity in COVID-19 pandemic
por: Palumbo Piergaspare, et al.
Publicado: (2021) -
Improving Forecast Reliability for Geographically Distributed Photovoltaic Generations
por: Daisuke Kodaira, et al.
Publicado: (2021) -
Allocation of risk factors for geodetic tasks in construction schedules
por: Kowacka Magdalena, et al.
Publicado: (2021) -
Influence of an extensive green roof in the non-linear structural behavior of self - construction households
por: Contreras,O., et al.
Publicado: (2021) -
Risk measurement of international oil and gas projects based on the Value at Risk method
por: Cheng Cheng, et al.
Publicado: (2018)