Evaluation of Project Duration Uncertainty using the Dependency Structure Matrix and Monte Carlo Simulations

The sequence of tasks is vital to the development of any project. The order of tasks is influenced by the information flow among them. The dependency structure matrix (DSM) can be used to model information flow. However, the information used by the DSM, including task duration, time required for com...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: Gálvez,Edelmira Delfina, Ordieres,Joaquin Bienvenido, Capuz-Rizo,Salvador Fernando
Lenguaje:English
Publicado: Escuela de Construcción Civil, Pontificia Universidad Católica de Chile 2015
Materias:
DSM
Acceso en línea:http://www.scielo.cl/scielo.php?script=sci_arttext&pid=S0718-915X2015000200010